Multiple Choice
Use the following MRP record to answer the question.
How large is the second planned order release?
A) less than or equal to 50 units
B) greater than 50 units but less than or equal to 100 units
C) greater than 100 units but less than or equal to 150 units
D) greater than 150 units
Correct Answer:

Verified
Correct Answer:
Verified