Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3.Which one of the following statements on item C is TRUE?
A) There will be no action notices for item C.
B) There will be exactly one action notice, to release a new order.
C) There will be exactly two action notices, to release a new order and delay the scheduled receipt.
D) There will be more than two action notices.
Correct Answer:

Verified
Correct Answer:
Verified
Q24: The quantity required of a dependent demanded
Q27: Explain the key differences between the FOQ,
Q78: Use the following MRP record to answer
Q81: The purpose of Finite Capacity Scheduling is
Q82: Table 13.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2786/.jpg" alt="Table 13.5
Q84: Complete the following MRP schedule:<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2786/.jpg"
Q85: A technique for projecting time-phased requirements for
Q139: Finite capacity scheduling is an algorithm designed
Q170: Service providers must plan for the same
Q172: ERP systems allow an organization to view