Multiple Choice
Table 13.1
-Use the following MRP record to answer the question.
What will be the projected on-hand inventory quantity in week 8?
A) less than or equal to 30 units
B) greater than 30 units but less than or equal to 60 units
C) greater than 60 units but less than or equal to 90 units
D) greater than 90 units