Multiple Choice
Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent.
A) 9 percent, accept
B) 9 percent, reject
C) 16.61 percent, accept
D) 16.61 percent, reject