Compute the NPV for Project X with the Cash Flows

Question 36

Multiple Choice

Compute the NPV for Project X with the cash flows shown as follows if the appropriate cost of capital is 10 percent.
 Time 01234 Cash Flow $100,000$36,000$200,000$210,000$10,006\begin{array} { l c c c c c c } \text { Time } & 0 & 1 & 2 & 3 & 4 \\\text { Cash Flow } & - \$ 100,000 & \mathbf { \$ 3 6 , 0 0 0 } & \mathbf { \$ } 200,000 & \mathbf { \$ 2 1 0 , 0 0 0 } & \mathbf { \$ } 10,006\end{array}


A) $183,507.96
B) $247,410.67
C) $248,962.50
D) $262,622.77