Multiple Choice
What is a production schedule specifying the sequence and critical path for performing the steps in a project called?
A) MRP chart
B) JIT chart
C) FMS chart
D) Pert chart
E) Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified