Multiple Choice
A firm is considering a project with a cash break-even point of 8,100 units. The selling price is $12.50 a unit and the variable cost per unit is $6.25. What is the amount of the total fixed costs?
A) $49,375
B) $49,875
C) $50,625
D) $51,125
E) $51,938
Correct Answer:

Verified
Correct Answer:
Verified