Multiple Choice
The ________ is also known as a PERT diagram or critical path diagram and is used in controlling projects.
A) affinity diagram
B) tree diagram
C) activity network diagram
D) cause-and-effect diagram
E) matrix diagram
Correct Answer:

Verified
Correct Answer:
Verified