    A Production Manager Wants to Design an Assembly Line That
Solved

A Production Manager Wants to Design an Assembly Line That

Question 67

Question 67

Multiple Choice

A production manager wants to design an assembly line that will turn out 800 widgets per day.There will be eight working hours in each day.What is the optimum cycle time?


A) 36 seconds
B) 60 seconds
C) 6 seconds
D) 3.6 seconds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q62: A manufacturer of detergent enhances their product

Q63: U-shaped production lines that are more efficient

Q64: Which option should be chosen if the

Q65: Use the information below to answer the

Q66: Quality Function Deployment is<br>A)a method for translating

Q68: Use the information below to answer the

Q69: A schematic picture of a process using

Q70: In Muther's grid the Symbol "I" represents<br>A)Absolutely

Q71: The "uptime" or proportion of time that

Q72: The model used in designing functional layouts

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines