Question 68

Multiple Choice

Use the information below to answer the following question(s) .
A production line operates for 450 minutes per day.Desired production volume is 80 units per day.Total task time to make the product is 56 minutes.
-What is the balance delay?


A) 88.88%
B) 0.44%
C) 66.67%
D) 33.33%

Correct Answer: