Multiple Choice
Paulina, a fashion designer, has a new project that requires her to make five dresses in seven days. A sum of $2,000 is allotted to her to fund the entire project. In three days, she completes one-third of the work and spends $1,200. Calculate the cost performance index from the given scenario.
A) 0.55
B) 0.75
C) 0.33
D) 0.66
E) 0.25
Correct Answer:

Verified
Correct Answer: