Multiple Choice
David, an architect, is in charge of executing a housing project. He appoints Charles to collect, record, and report all the necessary information to David and other relevant stakeholders. In this scenario, Charles will be engaged in _____ the project.
A) scoping
B) monitoring
C) planning
D) controlling
E) scheduling
Correct Answer:

Verified
Correct Answer:
Verified