Multiple Choice
Minkset Blu, a textile company, wants to improve its sales over a span of four years. In the first year, the company installs new looming machines that improve the production cost. However, it takes two years for the company to establish a liaison with online retailers to improve the accessibility of its products. This delays the company's goal of improving sales by a year. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM) , the set of activities that cause the delay are part of _____.
A) the Smith chart
B) the Portolan chart
C) the critical path
D) the throughput process
E) the control chart
Correct Answer:

Verified
Correct Answer:
Verified
Q7: The critical path always has the largest
Q8: What assumptions are made about the probabilities
Q9: A task or set of tasks required
Q10: Which type of precedence diagramming convention is
Q13: A start-to-finish linkage is the most common
Q14: A situation where two or more activities
Q15: The difference between the LST and EST
Q16: Henry Gantt developed the Gantt chart.
Q17: Rico Gen, a sports apparel manufacturing company,
Q28: What is a Gantt chart?