The Otero Manufacturing Company Collected the Following Information (In Days)

Question 75

Multiple Choice

The Otero Manufacturing Company collected the following information (in days) :
 April  Transporting product 2.0 Processing product 14.0 Inspecting product 0.5 Storing product 6.0\begin{array} { | l | r | } \hline & \text { April } \\\hline \text { Transporting product } & 2.0 \\\hline \text { Processing product } & 14.0 \\\hline \text { Inspecting product } & 0.5 \\\hline \text { Storing product } & 6.0 \\\hline\end{array}
-
What is the manufacturing cycle time?


A) 14.0 days.
B) 16.0 days.
C) 22.0 days.
D) 22.5 days.

Correct Answer: