Solved

The Everton Manufacturing Company Collected the Following Information (In Days)

Question 80

Essay

The Everton Manufacturing Company collected the following information (in days):
 April  May  June  Transporting product 2.03.02.0 Processing product 5.07.07.0 Inspecting product 0.50.81.0 Storing product 2.03.04.0\begin{array} { | l | r | r | r | } \hline &{ \text { April } } & \text { May } & { \text { June } } \\\hline \text { Transporting product } & 2.0 & 3.0 & 2.0 \\\hline \text { Processing product } & 5.0 & 7.0 & 7.0 \\\hline \text { Inspecting product } & 0.5 & 0.8 & 1.0 \\\hline \text { Storing product } & 2.0 & 3.0 & 4.0 \\\hline\end{array}
Required:
a. Calculate the manufacturing cycle efficiency for April, May, and June.
b. Calculate the processing time required for June so that the manufacturing cycle efficiency is equal to the most efficient of the previous two months.

Correct Answer:

verifed

Verified

a.April: [5.0/(2.0 + 5.0 + .5 ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions