Solved

A Project Consists of Four Consecutive Tasks That Have Average

Question 7

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's model to determine the aggregated buffer of one standard deviation for this project. A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)  as shown in the table. Use Newbold's model to determine the aggregated buffer of one standard deviation for this project.   A)  31 days B)  16 days C)  8 days D)  5 days


A) 31 days
B) 16 days
C) 8 days
D) 5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions