    A Project Consists of Four Consecutive Tasks That Have Average
Solved

A Project Consists of Four Consecutive Tasks That Have Average

Question 8

Question 8

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Goldratt's model to determine the aggregated buffer for this project. A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)  as shown in the table. Use Goldratt's model to determine the aggregated buffer for this project.   A)  20 days B)  10 days C)  15 days D)  5 days


A) 20 days
B) 10 days
C) 15 days
D) 5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: A project is represented by the activity

Q7: A project consists of four consecutive tasks

Q12: A project is represented by the activity

Q32: A feeder buffer is a buffer that

Q52: Compose a haiku using three or more

Q53: A system-wide constraint is called a:<br>A)Rope.<br>B)Resource.<br>C)Drum.<br>D)Chain.

Q61: Which adjective is most appropriate for Agile

Q64: Refactoring is the continuous process of streamlining

Q86: List any three criticisms of critical chain

Q95: What is the difference between the critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines