Solved

A Project Consists of Six Consecutive Tasks That Have Average

Question 49

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days)  as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.   A)  44 days B)  6 days C)  17 days D)  9 days


A) 44 days
B) 6 days
C) 17 days
D) 9 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions