Solved

A Project Is Represented by the Activity Durations (In Days

Question 45

Multiple Choice

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)  and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology?   A)  4 days B)  3 days C)  2 days D)  1 days


A) 4 days
B) 3 days
C) 2 days
D) 1 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions