Multiple Choice
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology?
A) 4 days
B) 3 days
C) 2 days
D) 1 days
Correct Answer:

Verified
Correct Answer:
Verified