Multiple Choice
Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4-day lag between activities C and B?
A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
Correct Answer:

Verified
Correct Answer:
Verified