A Project Has the Activity Duration and Cost Information Indicated

Question 81

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the cost of the least expensive project possible? A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the cost of the least expensive project possible?   A)  $11,450 B)  $12,450 C)  $13,450. D)  $14,450


A) $11,450
B) $12,450
C) $13,450.
D) $14,450