Multiple Choice
-Use the Gantt chart and activity list to determine when resource 3 is free.
A) Between 0 and 10
B) Between 10 and 20
C) Between 20 and 30
D) Between 30 and 40
Correct Answer:

Verified
Correct Answer:
Verified