    A Project Has the Activity Duration and Cost Information Indicated
Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 22

Question 22

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days? A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days?   A)  $172,000 B)  $218,000 C)  $192,000 D)  $159,000


A) $172,000
B) $218,000
C) $192,000
D) $159,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: The process of accelerating a project is

Q16: What is the duration of the project

Q18: Activity X has the start to finish

Q20: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7704/.jpg" alt=" -Use the Gantt

Q23: Use the information in the table (all

Q24: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7704/.jpg" alt=" -Use the Gantt

Q25: A project has the activity duration and

Q34: AOA is a more useful technique than

Q40: For large projects,network diagrams are more useful

Q55: An activity performed by a subcontractor is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines