Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. What is the highest total cost for completing this project?
A) $14,250
B) $13,950
C) $13,550
D) $13,150
Correct Answer:

Verified
Correct Answer:
Verified