A Project Has the Precedence Requirements and Activity Durations Shown

Question 63

Multiple Choice

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project?   A)  Combine activities A, B, C B)  Combine activities B, E, H C)  Combine activities E, F D)  Combine activities G, H, I


A) Combine activities A, B, C
B) Combine activities B, E, H
C) Combine activities E, F
D) Combine activities G, H, I