Multiple Choice
The overall effect of laddering activities is to:
A) Streamline the linkage and sequencing between activities and keep project resources fully employed.
B) Summarize some subsets of the activities identified in the overall project network.
C) Allow the project team to disaggregate the overall project network into logical summaries.
D) Allow the project manager to more fully deploy resources and complete the project with zero slack.
Correct Answer:

Verified
Correct Answer:
Verified