A project manager is using the net present value method to make the final decision on which project to undertake. The company has a 12% required rate of return and expects a 3% rate of inflation for the following four years. What is the NPV of a project that has cash flows as shown in the table?
A) -$9,762
B) -$56,859
C) -$69,387
D) -$98,780