A Project Manager Is Using the Net Present Value Method

Question 61

Multiple Choice

A project manager is using the net present value method to make the final decision on which project to undertake. The company has a 12% required rate of return and expects a 3% rate of inflation for the following four years. What is the NPV of a project that has cash flows as shown in the table? A project manager is using the net present value method to make the final decision on which project to undertake. The company has a 12% required rate of return and expects a 3% rate of inflation for the following four years. What is the NPV of a project that has cash flows as shown in the table?   A)  -$9,762 B)  -$56,859 C)  -$69,387 D)  -$98,780


A) -$9,762
B) -$56,859
C) -$69,387
D) -$98,780

Correct Answer: