Multiple Choice
A simple scoring model for project evaluation requires:
A) Importance weights from 1 to 10 assigned to each criterion.
B) Score values assigned to each criterion in terms of its rating.
C) A division of weights by scores to arrive at a standardized score for each criterion.
D) A summation for each criterion to achieve an overall criterion score.
Correct Answer:

Verified
Correct Answer:
Verified