Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by 6 weeks, what will happen to the expected time for that activity?
A) It will increase by 6 weeks.
B) It will decrease by 1 week.
C) It will increase by 1 week.
D) It will remain the same.
Correct Answer:

Verified
Correct Answer:
Verified