Multiple Choice
The estimation based on the experience of one or more experts on the particular activity or project is called:
A) published estimating data.
B) expert judgment.
C) bottom- up estimating.
D) alternatives analysis.
Correct Answer:

Verified
Correct Answer:
Verified