Multiple Choice
The critical path in a network diagram illustrates the:
A) effect of accumulated slack.
B) longest time in which a project is completed.
C) importance of resource leveling.
D) shortest time in which a project can be completed.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q96: The estimation of activities' durations using some
Q97: Free slack is also known as _
Q98: The activity resource requirements should include any
Q99: The actual time spent working on an
Q100: Using critical chain scheduling, a _ is
Q102: The estimation based on the experience of
Q103: _ is the process of estimating
Q104: The critical path is the _
Q105: The shortest time in which a project
Q106: Capital resources are the tools and