Multiple Choice
The estimation of activities' durations using some type of mathematical process is called:
A) mathematical estimating.
B) psychometric estimating.
C) econometric estimating.
D) parametric estimating.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q91: _ are probabilistic analyses used to
Q92: A _ is a control system developed
Q93: _ is the process of determining
Q94: Dates imposed to meet some type of
Q95: When managers choose one resource over others,
Q97: Free slack is also known as _
Q98: The activity resource requirements should include any
Q99: The actual time spent working on an
Q100: Using critical chain scheduling, a _ is
Q101: The critical path in a network diagram