Multiple Choice
________ is a technique that is used to estimate project duration when individual activity duration estimates are uncertain.
A) Likelihood procedure
B) Three- point estimate
C) OPR- method
D) PERT
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: Hard data from specific activities carried out
Q11: _ are probabilistic analyses used to
Q12: _ is an attempt to finish
Q13: The longest path through a network diagram
Q14: _ slack is the time an
Q16: The critical path method determines the sequence
Q17: The number of lines of code is
Q18: Resource leveling heuristics are _ used
Q19: List and describe the five techniques for
Q20: _ slack is the time and