Multiple Choice
The critical path method determines the sequence of task activities that directly affect the completion of a project by:
A) determining the longest path through a network diagram.
B) subtracting the shortest path from the longest path in a network diagram.
C) adding all activities in a network diagram.
D) determining the shortest path through a network diagram.
Correct Answer:

Verified
Correct Answer:
Verified