Multiple Choice
The approach to creating a WBS where all team members try to come up with as many tasks to complete the project as possible is called:
A) bottom- up planning.
B) Delphi technique.
C) top- down planning.
D) brainstorming.
Correct Answer:

Verified
Correct Answer:
Verified