Multiple Choice
The need to start marketing efforts long before a product launch at Microsoft is an example of the following constraint(s) :
A) safety and efficiency.
B) preferences and policies.
C) technical requirements and specifications.
D) resource availability.
Correct Answer:

Verified
Correct Answer:
Verified