Multiple Choice
_________are documented and authorized changes that are scheduled for implementation by the project team.
A) Approved preventive actions
B) Approved change requests
C) Approved corrective actions
D) Approved defect repair
Correct Answer:

Verified
Correct Answer:
Verified