menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Systems Project Management
  4. Exam
    Exam 12: Managing Project Control and Closure
  5. Question
    The_________ Is Calculated by Dividing the Original Time Estimate by the SPI
Solved

The_________ Is Calculated by Dividing the Original Time Estimate by the SPI

Question 46

Question 46

Multiple Choice

The_________ is calculated by dividing the original time estimate by the SPI.


A) estimated time to complete
B) completion time
C) estimated cost at completion
D) schedule performance index

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: The withholding of information for fearing negative

Q42: User training usually occurs after project handover.

Q43: One common determinant for the most appropriate

Q44: A negative CV means that it cost

Q45: The budgeted cost for the work scheduled

Q47: _are documented and authorized changes that are

Q48: Team members need to be encouraged to:<br>A)offer

Q49: In earned value management, for all variances,

Q50: _are activities and reporting methods instituted during

Q51: Indexes _indicate possible problems with a project's

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines