In Microsoft Project, the Correct Sequence of Defining a Project's

Question 45

Multiple Choice

In Microsoft Project, the correct sequence of defining a project's working time is:


A) select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B) select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C) select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D) select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.