Multiple Choice
In Microsoft Project, the correct sequence of defining a project's working time is:
A) select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B) select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C) select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D) select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.
Correct Answer:

Verified
Correct Answer:
Verified
Q40: In Microsoft Project, defining the project's working
Q41: A red bar in the resource graph
Q42: Microsoft Project determines the start and finish
Q43: It is not possible to set the
Q44: _ have a duration of zero.
Q46: Unfortunately, you cannot see the critical path
Q47: "Always track by entering the hours of
Q48: The resource graph view shows the:<br>A)percent of
Q49: By default, every task in Microsoft Project
Q50: The_ is a toolbar that includes