    It Is Not Possible to Set the Duration for Summary
Solved

It Is Not Possible to Set the Duration for Summary

Question 43

Question 43

True/False

It is not possible to set the duration for summary tasks in Microsoft Project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q38: The_ view shows the number of

Q39: If a task does not take a

Q40: In Microsoft Project, defining the project's working

Q41: A red bar in the resource graph

Q42: Microsoft Project determines the start and finish

Q44: _ have a duration of zero.

Q45: In Microsoft Project, the correct sequence of

Q46: Unfortunately, you cannot see the critical path

Q47: "Always track by entering the hours of

Q48: The resource graph view shows the:<br>A)percent of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines