Short Answer
To specify a day as non- working time, click on________ .
Correct Answer:

Verified
"Change Wo...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
"Change Wo...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Related Questions
Q1: Having too many people assigned to a
Q2: You can choose between all four task
Q3: Project can generate WBS numbering codes to
Q4: "Always track by entering the percent of
Q6: The_ column allows to specify the
Q7: In Microsoft Project, you can specify working
Q8: In Microsoft Project, once a critical path
Q9: The first time you assign resources to
Q10: For task durations, the default in Microsoft
Q11: Always track by entering the actual work