    The First Time You Assign Resources to a Task, Project
Solved

The First Time You Assign Resources to a Task, Project

Question 9

Question 9

True/False

The first time you assign resources to a task, Project calculates the duration of the task by multiplying the work required to complete the task by the percentage of work units.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: "Always track by entering the percent of

Q5: To specify a day as non- working

Q6: The_ column allows to specify the

Q7: In Microsoft Project, you can specify working

Q8: In Microsoft Project, once a critical path

Q10: For task durations, the default in Microsoft

Q11: Always track by entering the actual work

Q12: Microsoft Project determines the start and finish

Q13: You can group tasks into a summary

Q14: When scheduling tasks in Microsoft Project, you

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines