True/False
The first time you assign resources to a task, Project calculates the duration of the task by multiplying the work required to complete the task by the percentage of work units.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q4: "Always track by entering the percent of
Q5: To specify a day as non- working
Q6: The_ column allows to specify the
Q7: In Microsoft Project, you can specify working
Q8: In Microsoft Project, once a critical path
Q10: For task durations, the default in Microsoft
Q11: Always track by entering the actual work
Q12: Microsoft Project determines the start and finish
Q13: You can group tasks into a summary
Q14: When scheduling tasks in Microsoft Project, you