Multiple Choice
Which of the following is not a method of managing quality?
A) flexible manufacturing
B) continuous improvement
C) kanban
D) just- in- time
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q16: A Gantt charts list tasks, compared to
Q17: The transformation process is as relevant to
Q18: Application of PERT Network Analysis<br>Grace has just
Q19: The formula for productivity is _divided by
Q20: Application of PERT Network Analysis<br>Grace has just
Q22: The process of managing the entire sequence
Q23: Supply chain management focuses on the efficient
Q24: What are the four barriers to successful
Q25: Project management is the task of getting
Q26: What is just- in- time (JIT)inventory?