Multiple Choice
Application of PERT Network Analysis
Grace has just graduated from college with a degree in business administration and is totally overwhelmed by her first job. When she was in school, she could work on projects one at a time, and now she finds that she must juggle several projects with multiple activities. Grace is amazed that her supervisor, Linda, seems to have everything planned in a neat flowchart. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the actions that must take place, the major activities, and potential problems so she can be proactive.
-In PERT analysis, the longest or most time- consuming sequence of events and activities required to complete a project in the shortest amount of time is referred to as
A) critical path.
B) activities.
C) slack time.
D) events.
Correct Answer:

Verified
Correct Answer:
Verified
Q15: Management must provide value to customers. Value
Q16: A Gantt charts list tasks, compared to
Q17: The transformation process is as relevant to
Q18: Application of PERT Network Analysis<br>Grace has just
Q19: The formula for productivity is _divided by
Q21: Which of the following is not a
Q22: The process of managing the entire sequence
Q23: Supply chain management focuses on the efficient
Q24: What are the four barriers to successful
Q25: Project management is the task of getting