Application of PERT Network Analysis

Question 20

Multiple Choice

Application of PERT Network Analysis
Grace has just graduated from college with a degree in business administration and is totally overwhelmed by her first job. When she was in school, she could work on projects one at a time, and now she finds that she must juggle several projects with multiple activities. Grace is amazed that her supervisor, Linda, seems to have everything planned in a neat flowchart. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the actions that must take place, the major activities, and potential problems so she can be proactive.
-In PERT analysis, the longest or most time- consuming sequence of events and activities required to complete a project in the shortest amount of time is referred to as


A) critical path.
B) activities.
C) slack time.
D) events.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions