Multiple Choice
If a project requires coordinating hundreds of activities, some that must be done simultaneously and some that cannot begin until earlier activities have been completed, which of the following would be used?
A) break- even analysis
B) load chart
C) Gantt chart
D) PERT network analysis
Correct Answer:

Verified
Correct Answer:
Verified