Multiple Choice
Application of PERT Network Analysis
Grace has just graduated from college with a degree in business administration and is totally overwhelmed by her first job. When she was in school, she could work on projects one at a time, and now she finds that she must juggle several projects with multiple activities. Grace is amazed that her supervisor, Linda, seems to have everything planned in a neat flowchart. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the actions that must take place, the major activities, and potential problems so she can be proactive.
-If Linda and Grace work together developing a new product that will be tested in several markets, the best device to use for this project would be _____________.
A) a Production chart
B) a PERT network analysis chart
C) a load chart
D) a Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified
Q40: Application of Value Chain Management<br>Glenn is a
Q41: Three tools that can be used to
Q42: Choose the one statement below that is
Q43: Application of PERT Network Analysis<br>Grace has just
Q44: If a project manager notices some slippage
Q46: If a project requires coordinating hundreds of
Q47: Any event on the on the critical
Q48: Define the term "slack time" and describe
Q49: In Japan, just- in- time (JIT)systems are
Q50: Briefly describe project management.