Let B = Budgeted Total Cost for a Work Package

Question 49

Multiple Choice

Let B = budgeted total cost for a work package T = estimated completion time for a work package
P = percent complete
A = actual expenses to date
M = time used to date
What is the definition of cost overrun, C?


A) C = A - PB
B) C = A - (1 - P) TB
C) C = A - PTB
D) C = A - MB/T

Correct Answer: