In a PERT Network, You Are Given the Following Data

Question 54

Essay

In a PERT network, you are given the following data with times in weeks.  Activity  Immediate  Optimistic  Most Likely  Pessimistic  Predecessors  Time  Time  Time  A  G 1113 B 4920 C  A 21114 D  A, B 5613 E  D 3611 F  C, D 91011 G  E , F 72021\begin{array}{ccccc}\text { Activity } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\& \text { Predecessors } & \text { Time } & \text { Time } & \text { Time }\\\text { A } & -- & \text { G } & 11 & 13 \\\text { B } & -- & 4 & 9 & 20 \\\text { C } & \text { A } & 2 & 11 & 14 \\\text { D } & \text { A, B } & 5 & 6 & 13 \\\text { E } & \text { D } & 3 & 6 & 11 \\\text { F } & \text { C, D } & 9 & 10 & 11 \\\text { G } & \text { E }, \text { F } & 7 & 20 & 21\end{array}
A.What is the critical path?
B.What is the probability the project will be completed within one year (52 weeks)?

C.Which activity has the most slack?

Correct Answer:

verifed

Verified

A.
(A - C - F - G)

...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions