    What Is the Net Present Value for a Project Costing
Solved

What Is the Net Present Value for a Project Costing

Question 1

Question 1

Multiple Choice

What is the Net Present Value for a project costing $200,000 in the first year no discount) that produces a net benefit of $40,000/year for seven years when the discount rate is 7%?


A) $215,572
B) $15,572
C) 1.0779
D) 5 years

Correct Answer:

verifed

Verified

Related Questions

Q2: Advantages of a capital budget process include

Q3: What is the Benefit Cost Ratio for

Q4: Two government projects have the following benefit

Q5: When evaluating the viability of a project,

Q6: To what value would $20,000 compound in

Q7: Why are the capital costs of long-term

Q8: Which of the following is not a

Q9: Benefits received in the future are adjusted

Q10: Which of the following would be a

Q11: A lower discount rate applied to a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines