Multiple Choice
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?
A) Activity A
B) Activity C
C) Activity D
D) Activity G
Correct Answer:

Verified
Correct Answer:
Verified
Q64: The critical path is the _ path
Q65: Exhibit 15.6<br>The following questions use the information
Q66: Exhibit 14.13<br>The following questions use the information
Q67: Exhibit 15.3<br>The following questions are based on
Q68: Exhibit 15.2<br>The following questions employ the AON
Q70: Exhibit 14.13<br>The following questions use the information
Q71: Exhibit 15.1<br>The following questions employ the AON
Q72: If we are employing Activity-On-Arc (AOA) network